Village Projects

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Capital Improvement Program (CIP)

2024 Street Resurfacing Project

2024 Street Resurfacing Project Map

The Village of Carol Stream awarded the 2024 Flexible Pavement Street Resurfacing Project to Builders Paving on April 15th. This resurfacing work will include curb and sidewalk repairs where applicable, and then the removal and replacement of the street pavement.  The contractor plans to begin construction within the next few weeks, weather permitting.  They plan to finish construction by the end of August.  This project encompasses approximately three and a half miles of roadway throughout the Village.

The Contractor will be performing various forms of work on many streets throughout the Village and unforeseen circumstances such as weather and construction issues make it difficult to provide an exact date when the contractor will be performing a particular task adjacent to your home.  Updates on the construction progress can be found below. 

This type of construction can generate some inconveniences to residents that live adjacent to the roadway.  The Contractor will be instructed to provide access to your driveway as much as possible during work operations.  However, some exceptions will occur.  When new concrete curb or sidewalk is replaced adjacent to your driveway, you may lose access to your driveway for seven days or more while the concrete cures. While your driveway is inaccessible, arrangements have been made to allow overnight parking on your street and nearby streets.  You will not need to notify the Police Department for overnight parking on these nights.  A door hanger will be placed at your front door prior to undertaking work that will limit access to your driveway. You will find that when curbs and/or sidewalks adjacent to your driveway are repaired, a section of the driveway may be damaged.  The contractor will perform those driveway repairs after the installation of the new curb or sidewalk.

If you or anyone in your household has physical impairments and requires special arrangements, please call Engineering Services at (630) 871-6220.

Thank you for your patience and cooperation during this project.

 Street Resurfacing Construction Updates 
  • Week of May 20th - The contractor will saw cutting existing curb and sidewalk that will be removed and replaced.  Also, underdrain installation is expected to occur on Thunderbird Trail. 
  • June 3rd - June 28- The concrete contractor is performing curb and sidewalk removal and replacement throughout the project.
  • Week of July 1 - The storm sewer repair contractor is performing storm sewer structure repairs throughout the project and also installing underdrain on Evergreen Drive, Buffalo Circle and Fox Court.  
  • Week of July 8th - The asphalt contractor plans to begin milling the deteriorated pavement off of Kuhn Road and the residential areas north of Lies Road.  From there they expect to work their way to Thunderbird Trail, Appaloosa Court, and Osage Circle and then to Evergreen Drive, Buffalo Circle and Fox Court.   (It is very helpful to refrain from parking on these streets as the contractor performs this work.)
  • Week of July 15th - The asphalt contractor continues to mill the deteriorated pavement off of the streets throughout the project.  Asphalt driveway repairs are underway and roadway storm sewer repairs are underway. 
  • July 19th - The asphalt contractor will place the first layer of asphalt on Thunderbird Trail.  The roadway is open to local traffic at all times, however construction delays can be expected.  (It is very helpful to refrain from parking on the roadway as the contractor paves the road. )
  • Week of July 22nd - The asphalt contractor will continue with paving operations throughout the project limits.  The concrete contractor will complete curb and sidewalk installation in areas that were skipped for the storm sewer work.