Klein Creek Stream Bank Stabilization - Section I

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

SECTION I: THUNDERBIRD TRAIL TO KUHN ROAD

Project Manager: Gregory R. Ulreich, P.E., CFM
Webpage Last Updated: January 24, 2024

The project is currently in Phase III - Construction! For the latest updates and details, please refer to the "Phase III - Construction" tab further down this page.

A staff presentation was made to the Board of Trustees on November 1, 2021 (Presentation begins at 0:48 minute). The presentation provided a high-level overview of several design concepts that will be included with the construction of Section I. Click here to view the presentation as a PDF.

 

Check out the Village's YouTube page for a playlist of videos of construction:

20231204_164314485_iOS
IMG_3312
20231026_165741456_iOS
IMG_6202
IMG_6191
IMG_6197
IMG_5469
IMG_5464
2023-06-27 (6)

PHASE III OVERVIEW

The contractor, Earthwerks Land Improvement & Development, Corp., completed all major construction activity as of June 2023. 

Monitoring and Management of Native Vegetation

The subcontractor, ENCAP Incorporated, will be monitoring and managing the site during the 2023, 2024, and 2025 growing seasons. This mainly consists of mowing and applying herbicide to non-native, invasive species to give the native species time to establish. A prescribed burn is expected in 2025.

Their annual report summarizing the 2023 growing season showed that all performance criteria of the contract for the first year of growth has been met. Therefore, the project is well on its way to becoming a high-quality natural area with a diversity of species of native grasses, sedges, forbs, shrubs and trees. Great White Egrets, Mallard ducks, frogs, toads, turtles, minnows, left-handed snails, Kildeer, Sandpiper, songbirds, and insects have all been observed throughout 2023.

Klein Creek Trail (aka Multi-use Path)

The multi-use path between Bennett Drive (Easton Park Townhomes) and Arrowhead Trail (270-290) has been repaved. Two new extensions have been constructed to Kuhn Road and Thunderbird Trail, providing additional access points and connection to the Steven Ravenessi Trail and Bark Park. A safety railing along the retaining wall and final landscaping between the path and the residential properties is still needed along the Thunderbird Trail extension, which will be completed as weather permits.

In addition, the bridge behind the Water Reclamation Center (i.e. between 270 & 290 Arrowhead Trail) will be removed and replaced with a smaller, pedestrian-sized bridge that is higher and elevated above the flood height. The bridge is currently being fabricated and delivery/installation is estimated for late Spring / early Summer.

SCHEDULE

DATE DESCRIPTION OF UPDATE
   
2027 January  Contract Deadline: Accepting all plants, trees & shrubs.
2024 Spring Arrowhead Trail Bridge Removal & Replacement
2023 November Replanted 10 Native Trees & Shrubs (Did not survive initial planting)
2023 September Nearly 24,000 Plugs (All Native Species) Planted Along Streambanks & Wetlands
2023 June 100 Trees & 300 Shrubs Planted (All Native Species)
2022-08-03 Notices were mailed to residents adjacent to the worksite notifying them of the upcoming construction.
2022-08-03 The Village and Earthwerks conducted a pre-construction meeting. 
2022-05-02 Board of Trustees approved the award of a construction contract to Earthwerks Land Improvement & Development, Corp.